How Long Does Home Additions & ADU Take? Timelines and What to Expect
The contractor who tells you your ADU will be done in 90 days is probably right – about the construction phase. What they’re not telling you is that you’re likely 6 months away from that 90-day clock even starting. In Richmond, the time between signing a design contract and the first day a framer shows up regularly runs longer than the build itself, and most timeline conversations skip straight past it. This guide walks through every phase of a home addition or ADU project, how long each one actually takes in Richmond right now, and which early decisions quietly control whether you finish in 14 months or 26.
Quick Answer
A home addition or ADU in Richmond typically takes 12 – 20 months from first design meeting to final inspection. Of that, only 10 – 16 weeks is actual construction. Design and engineering run 4 – 8 weeks, City of Richmond plan check currently runs 8 – 14 weeks, and utility coordination with EBMUD and PG&E fills the gaps in between. Garage conversions move fastest because they often skip some utility work; new detached ADUs move slowest.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Table of Contents
- The Real Phase-by-Phase Timeline
- What Actually Controls Your Timeline in Richmond Right Now
- How Project Type Changes Duration
- The Week 1 Decisions That Compress or Extend Everything
- Utility Coordination with EBMUD and PG&E
- Holding Contractors to Milestones
- Common Mistakes to Avoid
- Frequently Asked Questions
The Real Phase-by-Phase Timeline
When contractors quote you “16 weeks,” they’re quoting the construction schedule. That number is real – but it’s the last quarter of the project. Here’s the full sequence as it plays out in Richmond, based on what we’ve seen across additions and ADUs in neighborhoods from the Richmond Annex to Point Richmond.
Phase 1 – Design and engineering (4 – 8 weeks). This covers architectural drawings, structural engineering, and site survey. A simple garage conversion may take 4 weeks. A two-story addition with a cantilevered second floor or a detached ADU on a sloped lot takes 8 weeks or more. Soil reports, if the site requires one, add 2 – 3 weeks on their own.
Phase 2 – City of Richmond plan check (8 – 14 weeks). This is currently the single longest phase that contractors rarely mention. Plan check timing depends on how complete your submittal is. Missing energy compliance forms, incomplete Title 24 documentation, or a structural calculation that doesn’t match the architectural plan will kick you back to the end of the queue.
Phase 3 – Utility coordination (2 – 10 weeks, variable). EBMUD handles water and sewer connection approvals. PG&E handles gas and electric service upgrades. New detached ADUs almost always require an electrical service upgrade or a new dedicated meter, and PG&E scheduling is the least predictable variable in the whole project. Get the application in during plan check, not after.
Phase 4 – Permits issued, construction begins (10 – 16 weeks). Foundation, framing, rough-in, insulation, drywall, finishes, final inspections. Garage conversions land near 10 weeks. Attached additions run 14 – 16. Weather in Richmond is usually cooperative, but winter rain still slows foundation work on sloped lots.
Phase 5 – Final inspections and closeout (1 – 3 weeks). Building, electrical, plumbing, and mechanical final sign-offs, plus any energy compliance verification.
What Actually Controls Your Timeline in Richmond Right Now
Homeowners assume the bottleneck is crew availability – that if you hired a faster builder, the project would finish faster. In Richmond in the current market, that’s not the constraint. The constraint is plan check backlog and utility scheduling, neither of which your contractor controls.
City of Richmond’s Building Division has been running 8 – 14 weeks on residential plan check for additions and ADUs. That’s the number you should plan around, not the construction schedule a contractor quotes you over the phone. We’ve seen submittals sit for 11 weeks, come back with three minor corrections, and then wait another 4 weeks for the second review – because corrections go back into the same review queue.
What compresses plan check time in Richmond:
- A complete submittal on the first pass. Missing Title 24 energy forms, incomplete structural calculations, and ambiguous site plans are the top three causes of rejection.
- A pre-application meeting. Richmond offers pre-submittal meetings for ADU projects, and showing up to one with a complete set of questions typically shaves 2 – 4 weeks off review.
- Hiring the structural engineer and architect at the same time. Sequential hiring adds 2 – 4 weeks. Parallel hiring saves them.
- Submitting the PG&E and EBMUD applications on the same day as the building permit application. Utility scheduling runs in parallel with plan check, not after it.
If a builder promises you a construction start date within 30 days of signing, ask them what their last three Richmond plan check turnaround times were. Real numbers, not averages. The answer tells you whether they’ve actually done this in Richmond recently.
How Project Type Changes Duration
Not all additions follow the same path. A garage conversion and a detached ADU start with the same architect but diverge sharply on permits, inspections, and utility work. Here’s how each type plays out in Richmond:
Garage conversion (8 – 14 months total). Fastest of the three. The structure exists, the foundation exists in most cases, and the utility runs are already on site. Plan check is often 6 – 10 weeks instead of 8 – 14 because the scope is narrower. Construction is 10 – 12 weeks. The catch: garage conversions trigger parking replacement requirements in some Richmond zones, and if you’re in a historic district, they may need design review that adds 4 – 6 weeks.
Attached addition (12 – 18 months total). New foundation, new framing, tie-in to the existing structure, and usually a kitchen or bathroom extension that pulls in plumbing and electrical. Plan check runs the full 8 – 14 weeks. Construction 14 – 16 weeks. Add 2 – 4 weeks for structural tie-in inspections that are specific to attached additions.
Detached ADU (14 – 20 months total). Slowest, and the reason is utility work. A detached ADU needs its own electrical service, its own water and sewer lateral (or a shared lateral with a submeter), and often a new gas line. PG&E scheduling is the wildcard here. We’ve seen service upgrade approvals come through in 3 weeks and we’ve seen them take 9. Plan check itself is usually the same 8 – 14 weeks as an attached addition, but the utility application should be filed in week one of design, not week one of construction.
For a deeper look at how each of these plays out on a specific site, our Home Additions & ADU in Richmond page walks through the permit and design sequence in more detail. If your project includes outdoor hardscape around the new structure, the Driveway & Pavers in Richmond page covers the site work sequencing that has to happen before foundation excavation.
The Week 1 Decisions That Compress or Extend Everything
Most of the schedule flexibility you’ll ever have in an ADU or addition project exists in the first week of design, before anything is finalized. After that, momentum takes over and every change costs 2 – 4 weeks. Here are the decisions worth making on day one:
- Confirm the zoning path before the architect starts drawing. In Richmond, ADU projects can go through a by-right path (over-the-counter review, faster) or a discretionary path (design review, slower). Knowing which one you’re in before the first sketch saves 4 – 8 weeks later.
- Pick the ADU type and size in week one. A 750 sq ft detached ADU and a 1,200 sq ft detached ADU have the same permit path but different structural engineering scope. Choosing in week one lets the engineer work in parallel with the architect instead of after.
- Decide on utility strategy immediately. Right now, on day one: are you upgrading service, sharing the existing service, or adding a new meter? Each choice has a different PG&E timeline, and the application has to match the design drawings.
- Hire structural engineering simultaneously with architecture. Not after. Simultaneous hiring compresses the design phase from 10 – 12 weeks to 6 – 8 on most projects.
- Submit Title 24 energy compliance with the first submittal. This is a document most homeowners don’t see, but missing it is the number one reason plan check gets kicked back in Richmond.
- Book the pre-submittal meeting. Richmond’s Building Division offers these. Thirty minutes with a plan reviewer in week two saves weeks of review in month three.
If you’re also planning to replace the fence line around the new structure while the site is torn up, our Fence Installation in Richmond page explains how to sequence that work with the foundation phase rather than after it. Getting the sequencing right on a project like this is one reason we walk every Richmond project through a full scoping conversation before design starts – those early conversations are the difference between a 14-month completion and a 22-month one.
Utility Coordination with EBMUD and PG&E
Utility scheduling is the phase that has no clean timeline and the phase contractors most often gloss over. Here’s what actually happens on a Richmond ADU project, and how to keep it from holding up construction:
- EBMUD water and sewer connection (3 – 8 weeks). For a detached ADU with a new sewer lateral, EBMUD review plus inspection typically runs 4 – 6 weeks. A shared lateral or submeter is faster. A new tap into a main in the street is slower and depends on water main capacity on your block.
- PG&E electrical service upgrade (3 – 10 weeks). This is the wildcard. If your panel is 100 amp and the ADU needs its own service, you’re looking at a 200 amp upgrade or a new dedicated meter. Either one requires a PG&E schedule review and sometimes a site visit from their engineering team. Applications started in week one of design usually clear before construction starts. Applications started after permits are issued routinely add 6 weeks to the construction phase.
- PG&E gas service (4 – 8 weeks). If the ADU needs a separate gas line and meter, treat it like electrical – file early, expect variability.
- Right-of-way and street work permits (2 – 4 weeks). If the sewer tap requires digging in the public right-of-way, the City of Richmond issues a separate encroachment permit. This is often missed and adds 2 – 4 weeks if it comes up after construction starts.
The strategy that works: file EBMUD and PG&E applications on the same day as your building permit submittal. Yes, before the permit is approved. The utility companies review their piece in parallel with the city. When construction starts, service is ready. When applications wait for permit issuance, construction starts, then stops for 6 weeks while PG&E schedules an inspection. That’s the scenario that turns a 14-month project into a 20-month project.
Holding Contractors to Milestones
The most important piece of a construction contract for a Richmond addition or ADU isn’t the price schedule. It’s the milestone language. Here’s how to read it and what to insist on:
Separate construction milestones from pre-construction milestones in writing. A good contract breaks the project into dated milestones: design complete, plan submitted, plan approved, utility applications filed, construction start, framing complete, rough-in complete, final inspection. Each one has a date or a duration.
Distinguish delays the contractor controls from delays they don’t. If plan check runs 14 weeks instead of 8, that’s not a contractor delay – but the contractor should have told you 8 – 14 weeks was the range, not 8 weeks firm. If the contractor’s engineer doesn’t finish structural drawings on schedule, that IS a contractor delay. The contract should say so explicitly.
Attach the schedule as an exhibit. Verbal schedule promises are worthless. The milestone table belongs in the contract, signed, with dates.
Define what “substantial completion” means. It should be defined as final inspections passed, not “walkthrough with punch list noted.” Those are different things and they can be 6 weeks apart.
Require weekly written status updates. A one-paragraph email each Friday stating what was completed last week, what’s scheduled next week, and any open items. This is not unreasonable to ask for on a $200K project, and it prevents small delays from compounding.
Groundwork Construction Co. of Richmond writes every project on the 730-Day Done Right Promise – if it’s not done right, we make it right – and that guarantee is only real if the project actually gets built. That’s why we do written milestone schedules with every Richmond addition and ADU contract. Calls come to a live person 24/7 if you have a scheduling question, not a voicemail that waits until Monday morning.
Common Mistakes to Avoid
- Believing the “construction only” timeline. A contractor who quotes “16 weeks” is quoting the last quarter. Ask for the total project duration from design to final inspection, and ask whether that includes plan check and utility work. If not, ask for the full breakdown in writing.
- Hiring the architect and structural engineer sequentially instead of in parallel. Four to six weeks lost, every time, and it’s the easiest delay in the whole project to prevent. Get both under contract in the same week.
- Waiting to file utility applications until the permit is issued. This one habit converts 6-week utility time into 12-week utility time and usually delays the foundation pour by a month or more.
- Submitting an incomplete plan set. Missing Title 24 energy compliance, incomplete structural calculations, or a survey that doesn’t match the site plan will send you back to the end of the review queue in Richmond. Review the submittal checklist against the actual package before it goes in.
- Assuming all ADU paths are the same. A garage conversion of an existing detached structure often moves through a faster permitting path than a new detached ADU, especially in older Richmond neighborhoods where the existing garage was already permitted. Confirm before design freezes.
- Not walking the site budget before design starts. A sloped lot in the Richmond Hills or a site with a constrained side yard often requires additional foundation or drainage work that isn’t seen until design begins. Scoping the site early saves weeks of redesign later.
- Skipping the pre-submittal meeting. Richmond offers them for ADU projects. They take 30 minutes and often save 3 – 4 weeks of back-and-forth review. Skipping them is a self-inflicted delay.
When to Call a Professional

A home addition or ADU involves structural engineering, permit coordination, utility work, and multiple inspection phases. If any of these are outside your comfort zone, call a licensed contractor before design starts, not after. The specific situations that warrant a call now: you’re in a Richmond historic district and don’t know whether the project needs design review; you don’t know whether your site requires a soil report; your PG&E panel is 100 amp and you’re planning a detached ADU; your architect has proposed a design but you haven’t scoped utilities or site drainage; or you’ve gotten two bids and the timelines are wildly different – that difference usually means one contractor is quoting construction only, and the other is quoting the whole project.
Groundwork Construction Co. of Richmond offers free estimates and design consults in Richmond – call (833) 700-4611. We’ll walk the site, review your utility situation, and give you a written milestone schedule with the actual plan check times we’re seeing in Richmond right now, not the ones that make the timeline look shorter. Funding matters too, so every project over $10,000 qualifies for $1,000 off, and 0% financing for 18 months is available. Our technicians have up to 12 years of experience, and every project is covered by the 730-Day Done Right Promise: if it’s not done right, we make it right. You can see how we handle full-scope work from foundation to finish line on our Groundwork Construction Co. of Richmond home page.
Frequently Asked Questions
An ADU in Richmond takes 12 – 20 months from first design meeting to final inspection, with 10 – 16 weeks of that being construction. The rest is design, City of Richmond plan check (currently 8 – 14 weeks), and utility coordination with EBMUD and PG&E. A garage conversion typically runs toward the shorter end; a detached new ADU runs toward the longer end because of utility service work.
Call (833) 700-4611 for a free estimate that includes a written milestone schedule specific to your site.
Because some contractors quote construction duration only and others quote the full design-through-final-inspection timeline. A construction-only quote of 14 weeks and a full-project quote of 15 months can both be accurate descriptions of the same project. Ask every contractor to confirm exactly what their timeline includes before you compare them.
Call (833) 700-4611 and we’ll break down the phases in writing so the estimates actually compare to each other.
You can, in three ways: submit a fully complete package on the first pass (Title 24, structural, site survey all included), book a pre-submittal meeting with Richmond’s Building Division before submission, and consider an over-the-counter path where the project scope qualifies. On a recent ADU in the Richmond Annex, running these three steps brought a 14-week plan check down to 9 weeks.
Call (833) 700-4611 to schedule a design consult and we’ll tell you which path your specific project qualifies for before you commit to a design.
Yes, a garage conversion is an ADU in California and in Richmond, but it typically takes 2 – 6 months less than a new detached ADU. The structure and foundation already exist, utility runs are already on site in most cases, and the permit scope is narrower. Plan check usually runs 6 – 10 weeks versus 8 – 14. The main variable is whether the garage is in a historic district or a zone that requires parking replacement.
Call (833) 700-4611 to find out which path your Richmond garage qualifies for.
In our experience, the three biggest causes of delay are: an incomplete permit submittal that gets rejected and re-queued, a PG&E service upgrade that wasn’t filed until after construction started, and a change order made after design froze. Together those three situations regularly add 4 – 6 months to a Richmond project. Every one of them is preventable with proper front-end sequencing.
Call (833) 700-4611 for a free project estimate that documents the sequencing up front, in writing.
It shouldn’t on a properly scoped project. Upfront pricing means the number in the contract is the number you pay – that’s the standard we hold on every Richmond project, and it’s why we put scope and schedule in the contract together. Change orders should only come from documented site conditions that were unknown before design, and those get priced in writing before any work starts. Insist on that contract language from any contractor. Call (833) 700-4611 to schedule a free estimate and design consult.
The Bottom Line
The construction phase of a Richmond addition or ADU is 10 – 16 weeks. The full project is 12 – 20 months. The gap between those two numbers is where most timeline conversations go wrong, and it’s where homeowners lose the most time. Design and engineering take 4 – 8 weeks; City of Richmond plan check runs 8 – 14 weeks right now; utility coordination with EBMUD and PG&E fills the gaps in between and can add 6 weeks on its own if the applications wait. The decisions that compress your timeline are made in week one of design: parallel hiring, complete submittals, utility applications filed on day one, and milestone language in the contract that separates contractor delays from plan-check delays. That’s the whole game. Get those right and your project finishes when it should. Get them wrong and the “90-day build” becomes month 20 of a very long project. Groundwork Construction Co. of Richmond handles the full scope from foundation to finish line, backs every project with the 730-Day Done Right Promise, and answers the phone live 24/7. Call (833) 700-4611 to schedule your free estimate and design consult.
Written by the team at Groundwork Construction Co. of Richmond.