How Long Does Windows & Doors Take? Timelines and What to Expect
A single window replacement takes half a day. A full-house window replacement on a 1,500 sq ft Richmond bungalow takes 2 – 4 days of install time, plus 6 – 12 weeks of lead time if you’re ordering custom sizes, which most older homes require. That gap is the whole story: the same phrase, “a few days,” gets used to describe a $400 swap and a $28,000 whole-house job. In this guide we’ll lay out realistic day counts by scope, why custom orders for pre-war Richmond housing stock stretch into the 8 – 12 week range, how Contra Costa County permit inspections fold into the schedule, and how a November door replacement differs from a July one. You’ll leave knowing exactly what timeline to expect for the job you’re actually having done.
Quick Answer
Most window and door projects run a total of 7 – 16 weeks from order to final walkthrough: 6 – 12 weeks of lead time for custom units, 1 – 4 days of installation depending on scope, and same-day or next-day permit inspection on exterior work requiring it. A single stock-size window or door can be done with far less lead time if the size is standard and the opening is straightforward.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
Table of Contents
- Timelines by Scope: Single Window to Full House
- Why Custom Windows for Richmond’s Old Housing Stock Take 8 – 12 Weeks
- Permits and Inspections in Richmond and Contra Costa County
- Bay Area Weather Windows
- What “One-Day Installation” Really Means
- Door Replacement Timelines
- How to Schedule Your Project
Timelines by Scope: Single Window to Full House
Here’s what we’ve actually seen across Richmond jobs, broken down by scope so you can match your project against a real number instead of a hand-wave.
- Single window replacement: Half a day of install. Lead time depends heavily on whether the size is standard stock (2 – 3 weeks) or custom-built to fit an old rough opening (8 – 12 weeks).
- Multi-window retrofit (3 – 5 windows): 1 – 2 days install. Same lead-time rules apply. Retrofit installs fit into existing frames, so they move faster than full tear-outs.
- Full-house window replacement, tear-out (10 – 20 windows): 2 – 4 days install on a typical 1,500 sq ft Richmond bungalow. Tear-outs expose framing, so add a day for trim and finish work.
- Single door replacement (entry or patio): Half day. A pre-hung unit fits where the old one came out with minimal framing; a slab replacement on an existing frame is faster; a slider or French door install runs longer.
- Multi-door project (3+ doors): 1 – 2 days install.
Add lead time on top of every one of those install numbers. The install is the visible event, but the schedule that actually matters starts when you place your order. If you’re ordering through a partner like Andersen or Pella, the factory lead time drives everything, and we plan your install date around it rather than promising a date the factory can’t meet. That’s the difference between a realistic schedule and a surprise in week three.
Why Custom Windows for Richmond’s Old Housing Stock Take 8 – 12 Weeks
Richmond’s housing stock is old. Bungalows in the Point Richmond and Iron Triangle neighborhoods, the 1920s – 1940s four-squares off Cutting Boulevard, the post-war tract homes in North Richmond and Parchester Village: these homes were not built to a modern standardized rough opening. Every window was framed in the field, which means the rough openings vary from one side of a house to the other, sometimes by a quarter inch or more.
Standard stock-size windows won’t fit those openings cleanly. You either order custom-built units sized to the measured opening, or you accept a retrofit frame plus filler trim, which is faster but visibly alters the opening. Custom sizing is the correct answer for pre-war Richmond homes, and it’s why our typical lead time on a full-house replacement here runs 8 – 12 weeks rather than the 2 – 3 weeks a builder-grade new-construction order would take.
The practical implications:
- Measure and order first. Every window gets field-measured before the order is placed. This adds a week to the front end but prevents fit problems later.
- Expect factory lead times of 8 – 12 weeks on custom units. Weather, factory capacity, and glass type all affect this. Tempered or specialty-coated glass adds time.
- Plan your install date around the order, not the other way around. If you’re targeting a spring install, order in December or January.
If you’re weighing a window project alongside other exterior work this year, our guide to Fence Installation in Richmond follows the same principle: order material early, install when it lands. Foundation-to-finishline scheduling is one reason homeowners consolidate exterior projects with Groundwork Construction Co. of Richmond home services, since one crew, one schedule, and one warranty covers it all.
Permits and Inspections in Richmond and Contra Costa County
Exterior window and door replacement generally requires a permit in Richmond when you’re changing the size of the opening, altering the structural framing, or installing a new egress window (required in bedrooms and basements by code). Like-for-like replacement in the same opening with the same size often doesn’t require a permit, but the rules tighten on anything structural. The City of Richmond Building Division issues residential permits, and inspections are performed by city inspectors, not private firms, on the standard schedule.
Here’s when to schedule the inspection relative to install:
- Framing and water-resistant barrier inspection: after the old unit is out, framing is squared and shimmed, and the WRB and flashing are installed but before the interior and exterior trim go on. The inspector needs to see the flashing detail.
- Final inspection: after install, flashing, trim, and weather-sealing are complete. This is typically the same day as finish work or the next business day.
The permit itself takes 1 – 3 weeks to issue in Richmond depending on the current queue, so build that into your schedule. When you’re working with a partner, the permit gets pulled under the General Contractor’s license and the inspection gets scheduled by that partner, which matters if you’re coordinating multiple trades. If you’re also planning an ADU project this year, Home Additions & ADU in Richmond covers how ADU permits layer onto standard residential permits, since ADU reviews run a different, longer queue.
Bay Area Weather Windows
Window and door replacement is exterior work, which means weather scheduling isn’t optional. A November door replacement in Richmond is a genuinely different conversation than a July one, and we plan them differently.
From roughly November through March, Bay Area rain events pass through in 2 – 4 day windows. During those months, we schedule exterior installs against the forecast and build in weather days. A door replacement in the rain months means prioritizing the unit that needs it most (an entry door with a failed seal, a patio door with a broken lock) and being honest about the risk of pushing a multi-door project into December. Windows installed in the wet season get extra attention to flashing detail and weather-sealing, and we won’t leave an opening uncovered overnight if the forecast shows rain.
From roughly April through October, the weather window opens right up. Dry, consistent days mean full-house installs proceed on schedule without weather interruptions, trim sealants cure properly, and final inspection isn’t delayed by a soaked install day. If you have flexibility, a spring or early-fall install of exterior windows and doors almost always goes more smoothly than a mid-winter one.
One Richmond-specific note: wind exposure on the hillside properties in Point Richmond and El Sobrante adds a scheduling factor. High-wind days aren’t install days for large units, and products in these areas should be rated for the wind exposure of the site.
What “One-Day Installation” Really Means
“One-day installation” is a real marketing phrase, and it’s not a lie in every case: a single stock-size window swap, a single door slab replacement, and some retrofit-style installs genuinely finish inside a day. But the phrase gets applied to full-house replacements that don’t finish in a day, and it gets applied by crews who compress the finish work to hit the promise.
A complete, properly flashed and finished installation on a full-house tear-out involves these steps, and they don’t all happen in one day:
- Removal and disposal of old units (2 – 4 hours for 10+ windows)
- Framing inspection and squaring of the rough opening
- Water-resistant barrier and flashing install, the step that determines whether water gets behind the unit in ten years
- Unit install, shimming, and leveling
- Interior trim and casing
- Exterior trim and sealant
- Final inspection and function test
When you hear “one day,” ask what’s included and what’s deferred. A one-day full-house replacement usually means interior trim gets scheduled for a separate visit, or exterior sealant is rushed. A properly finished install includes all of the above, and on a ten-window house, that’s a day and appropriately halfway through a second. We complete installs on a schedule we committed to in writing, and the 730-Day Done Right Promise backs the finish work: if the trim pulls, a sealant fails, or a unit doesn’t operate correctly, we make it right for two full years after install.
Door Replacement Timelines
Doors move faster than windows on lead time, since standard door sizes really are standard (32″, 34″, 36″ by 80″ runs are near-universal). The variables are style, material, and what’s behind the old frame.
- Entry door, pre-hung, standard size: 4 – 6 hours install; stock doors available in 1 – 2 weeks
- Entry door, custom size or premium material (wood, fiberglass in a custom configuration): 6 – 10 weeks lead; half a day install
- Patio slider: 4 – 6 hours install; lead time depends on whether the opening matches a stock slider size
- French door pair: full day install; 4 – 8 weeks lead
Two things drive door timelines longer than people expect. First, an old door frame often reveals rot behind it. If the sill plate or a jack stud is soft, you’re looking at framing repairs that add a day. Second, a new premium door in a Point Richmond or North & East home often needs custom trim and casing to match the house’s existing style, and that’s a finish-carpentry task, not a unit-install task. Budget the extra day for it.
How to Schedule Your Project
Here’s the sequence we recommend for Richmond homeowners, whether the project is one window or twenty:
- Get a free estimate and design consult. We measure on site, confirm scope and material, and put an upfront price in writing. No-hassle pricing, no surprises.
- Place the order early. If you’re ordering custom sizes, order 10 – 12 weeks before your target install date.
- File the permit if required. Permit issuance runs 1 – 3 weeks in Richmond.
- Confirm install date against the factory lead time and the weather forecast (dry season for preference, wet season with weather days built in).
- Install, inspect, finish. Framing and WRB inspection mid-install, final inspection after trim and sealant, then a walkthrough with you.
If you’re coordinating this alongside other exterior improvements, the same sequence applies to Driveway & Pavers in Richmond, where lead times on pavers and material delivery drive the schedule. One crew, one calendar, and one warranty covering multiple trades is the cleanest way to run a project like this.
Common Mistakes to Avoid
- Ordering your windows before the rough openings are measured. On an old Richmond bungalow, the openings almost never match the “as-built” dimensions. Measure first, order second. Ordering off the original plans from the 1940s is a guaranteed fit problem.
- Booking install for a wet-season week without a weather buffer. A November install needs weather days built into the schedule. Skipping them means either a rushed install or a reschedule, and both cost you. Build in two weather days per wet-season project.
- Treating “one day install” marketing as a full-house number. It usually isn’t. If the quote lists a full-house replacement at one day install, ask what gets deferred to a second visit. The answer tells you whether the finish work is real or rushed.
- Assuming permits aren’t needed. A like-for-like replacement often doesn’t need one, but any size change, structural change, or new egress window does. Cutting a larger opening without a permit is the mistake that surfaces at resale.
- Scheduling inspection too late. The framing and WRB inspection has to happen before trim goes on. If you schedule it after interior trim is installed, the inspector may require trim removal, which adds days and cost.
- Ignoring wind exposure on hillside properties. Units in Point Richmond and hillside El Sobrante should be selected and sealed for high wind. A low-rated unit there fails the seal faster, and a second install in year five is a bigger cost than doing it right the first time.
- Not asking about the workmanship warranty before signing. Any contractor should be able to tell you exactly what’s covered and for how long. The 730-Day Done Right Promise is our number: two full years of workmanship coverage from install, in writing.
See the difference
Before
After
Before
After
Before
AfterWhen to Call a Professional
Window and door replacement is not a do-it-yourself project when it involves anything beyond a single stock-size slider in a modern opening. Call a licensed contractor if: the old unit is a full tear-out with framing exposed, the opening will change size, the install requires a permit or new egress window, the door frame shows rot or the sill plate is soft, the unit is above ground level on a steep grade, or the project is a multi-unit or whole-house replacement. Getting flashing and sealant wrong on a window install is a slow-motion water-damage problem that takes years to surface and thousands to fix; it’s not a place to experiment. Groundwork Construction Co. of Richmond offers free estimates in Richmond – call (833) 700-4611. We’ll measure on site, put the number in writing, and tell you exactly what your install timeline looks like once the units are ordered.
Frequently Asked Questions

From order to final walkthrough, most Richmond window projects take 7 – 16 weeks total: 6 – 12 weeks of lead time for custom units, 1 – 4 days of installation, and same-day or next-day permit inspection on permitted work. A single stock-size replacement can be finished in far less. Call (833) 700-4611 for a free estimate and a timeline specific to your home’s measurements.
Not during active rain, no. We schedule exterior installs against the forecast during the wet months and build in weather days. Once the opening is cut, we don’t leave it uncovered overnight, which is why wet-season installs get scheduled conservatively. If you’re ordering in summer, you can safely plan a dry-season install in spring or fall.
A like-for-like replacement in the same opening often doesn’t require a permit in Richmond, but anything involving an opening-size change, structural framing alteration, or new egress window does. Permit issuance runs 1 – 3 weeks through the City of Richmond Building Division. Call (833) 700-4611 for a free estimate: we’ll confirm the permit requirement for your specific project in writing.
Install time on a typical 1,500 sq ft Richmond bungalow is 2 – 4 days. Add a day if it’s a full tear-out with trim and finish work exposed. But the total schedule is driven by the custom-unit lead time, which runs 8 – 12 weeks for pre-war Richmond housing stock. Plan for a 10 – 14 week project end to end.
An entry door install is half a day on a clean opening. It stretches to a day or more when the old frame reveals rot, the new door requires custom casing to match the house, or the opening needs framing repair. On older Richmond homes, plan for a full day and a possible second half-day for finish work. Call (833) 700-4611 to schedule a free estimate and we’ll give you a real number.
A retrofit install fits a new unit inside the existing frame, which is faster (1 – 2 days for a multi-window job) and less invasive. A full tear-out removes the frame entirely, which exposes the rough opening and allows proper flashing and framing inspection. Tear-out takes 2 – 4 days on a full-house replacement but lasts longer. We’ll tell you which is right for your Richmond home at the estimate.
The Bottom Line
The window and door timeline you get should match the job you’re actually having done. A single stock-size replacement is a half-day install with a short lead. A full-house replacement on old Richmond housing stock is a 10 – 14 week project end to end, driven by custom-unit lead times, permit issuance, and the weather window. The critical scheduling move is ordering early, 10 – 12 weeks before you want to install. The critical quality move is not accepting a rushed one-day promise on a job that genuinely needs more. And the critical trust move is getting the price and the warranty in writing before you sign: upfront pricing, no surprises, and the 730-Day Done Right Promise backing the finish work for two full years.
If you’re ready to lock in a real timeline for your Richmond window or door project, call (833) 700-4611 for a free estimate. Live person, 24/7. We’ll measure on site, give you the number in writing, and put the schedule in a form you can hold us to.
Written by the team at Groundwork Construction Co. of Richmond.